Work along Plymouth Road railroad embankment wash-out nears final phase
A work crew from the City of Ann Arbor removes soil and debris Monday morning to restore a wetland area at the base of a railroad embankment parallel to Plymouth Road in Ann Arbor. The embankment (on the left) washed out last year after a heavy rainfall, sending soil and debris across Plymouth Road east of Moore Street.
Amy Biolchini | AnnArbor.com
A 45-foot-long section of embankment washed out from under a line of railroad tracks after 3 inches of rain fell in a 24-hour period May 25, 2011. About 2,000 cubic yards of soil as well as trees that washed out from the embankment blocked the five-lane roadway for two days.
City crews are in the last week of their four-week contract to remove debris and soil from the land at the base of the embankment adjacent to the roadway -- a bill of $52,000 to date.
The area is being restored to a wetland. As the soil is cleared away, city crews are performing rough grading on the site. Workers said the original wetland had filled up with sediment over the years.
An excavator loads dirt into a truck at a wetland area along a railroad embankment parallel to Plymouth Road in Ann Arbor that washed out last year.
A $97,687.50 contract with Fonson Inc. for the final grading and construction of the wetland, including plant installation, should come before the Ann Arbor City Council July 16 for approval.
The final phase of work should begin in mid-August and be finished by the end of October, said city spokeswoman Lisa Wondrash.
Two new drainage pipes were also installed to replace old ones, said Andy Fischer, lead field operator for the project.
Drainage pipes that ran through the embankment before the washout had become clogged, Fischer said, and that likely contributed to the failure of the embankment.
Both pipes feed into a small creek.
Major repairs to the railroad embankment itself were previously completed by the Ann Arbor Railroad Company, which owns the tracks.

AnnArbor.com